Installations

Cirrus Water has been designing and building Atmospheric Water Generators for over 10 years. This experience has provided us with the expertise to solve complex problems that require specialized knowledge and advanced manufacturing capabilities.

Our team of engineering consultants, in conjunction with our shop technicians can design and build complete systems capable of delivering water to any size project from large commercial or industrial buildings to residential homes.

The following installations provide sustainable water solutions to a range of industries.

Case Studies

 
  • Installation done at Standard Bank Fish Hoek June 2018
  • Produces an average of 500 litres per day
  • Storage capacity of 1500 litres ( 2 x 750 litre slim line tanks linked)
  • Required to install tanks inside the branch, which required a drip tray and overflow pipes
  • Only access to roof was through small trap door – required us to rig the container and coil into position seperatly
  • Plumbed into buildings main supply

Read More

  • Installation done at Altron February 2018
  • 3 days to install
  • Had to hire riggers to scale the building and lay the piping 7 floors high.
  • There were noise complaints, so we specially designed a sound attenuator to dampen the sound of the fan
  • We have plumbed the water into 6 direct feed dispensers on each floor of the Altron building
  • Produces average of 500 litres per day
  • Storage capacity of 6000 litres .

Read More

  • Household installation for a client in Port Elizabeth July 2018
  • Produces an average of 200 litres of high quality drinking water per day
  • 10 000 litres storage capacity interlinked
  • Removed electric fencing to get tanks into position
  • Uses water for drinking and linked to irrigation system

Read More

  • Installation for Makro Montague Gardens July 2018
  • Had limited space for the amount of AWG’s requested – special frames were built in order for us to stack one on top of the other
  • Produces on average 4000 litres of high quality drinking water per day

Read More

  • Installation at Makro Ottery September 2018
  • An issue with space caused us to build a specialised frame and platform to hold the machines and tank
  • Storage capacity of 5000 litres
  • Produces on average 1500 litres of high quality drinking water per day
  • Plumbed into the buildings main water supply
  • Difficulties were coordinating project timing with contractors

Read More

  • Installation for Cape Nature Riverlands September 2018
  • Two days for cilvils and installation
  • Slabs and stones were put either side of the machine to reduce the amount of sand blown
  • Produces an average of 1000 Litres high quality drinking water per day
  • Plumbed into the main house water supply
  • Storage capacity of 5000 litres

Read More

  • Installation for Cape Nature Rocherpan September 2018
  • 4 days to do all the civil work (Trenches, clearing bushes and shrub for machines, laying on concrete slabs for solar)
  • 3 weeks in total from start to finish , to complete the project
  • Produces on average 2000 litres of high quality drinking water per day
  • Solar is saving around R200 000 of electricity per year
  • 300 metre plumbing and electrical run
  • Bottling and filling station installed

Read More

  • Installation at Fruitspot Cape Town October 2018
  • 4 days to level site for machines and tanks
  • Will produce an average of 5000 litres high quality drinking water per day
  • 50 000 litres storage capacity
  • Water will be pumped into existing storage tanks which are connected to buildings main supply
  • Took 2 days to get machines into place
  • Very little space on the side of the building, had to push machines one by one and rigged them into position

Read More

Installations

 
  • Installation done at Standard Bank Fish Hoek June 2018
  • Produces an average of 500 litres per day
  • Storage capacity of 1500 litres ( 2 x 750 litre slim line tanks linked)
  • Required to install tanks inside the branch, which required a drip tray and overflow pipes
  • Only access to roof was through small trap door – required us to rig the container and coil into position seperatly
  • Plumbed into buildings main supply

Read More

  • Installation done at Altron February 2018
  • 3 days to install
  • Had to hire riggers to scale the building and lay the piping 7 floors high.
  • There were noise complaints, so we specially designed a sound attenuator to dampen the sound of the fan
  • We have plumbed the water into 6 direct feed dispensers on each floor of the Altron building
  • Produces average of 500 litres per day
  • Storage capacity of 6000 litres .

Read More

  • Household installation for a client in Port Elizabeth July 2018
  • Produces an average of 200 litres of high quality drinking water per day
  • 10 000 litres storage capacity interlinked
  • Removed electric fencing to get tanks into position
  • Uses water for drinking and linked to irrigation system

Read More

  • Installation for Makro Montague Gardens July 2018
  • Had limited space for the amount of AWG’s requested – special frames were built in order for us to stack one on top of the other
  • Produces on average 4000 litres of high quality drinking water per day

Read More

 
  • Installation at Makro Ottery September 2018
  • An issue with space caused us to build a specialised frame and platform to hold the machines and tank
  • Storage capacity of 5000 litres
  • Produces on average 1500 litres of high quality drinking water per day
  • Plumbed into the buildings main water supply
  • Difficulties were coordinating project timing with contractors

Read More

  • Installation for Cape Nature Riverlands September 2018
  • Two days for cilvils and installation
  • Slabs and stones were put either side of the machine to reduce the amount of sand blown
  • Produces an average of 1000 Litres high quality drinking water per day
  • Plumbed into the main house water supply
  • Storage capacity of 5000 litres

Read More

  • Installation for Cape Nature Rocherpan September 2018
  • 4 days to do all the civil work (Trenches, clearing bushes and shrub for machines, laying on concrete slabs for solar)
  • 30% - 40% Cost of power savings per annum which equates to +-R50 000pa
  • 3 weeks in total from start to finish , to complete the project
  • Produces on average 2000 litres of high quality drinking water per day
  • Solar is saving around R105 000 of electricity per year
  • 300 metre plumbing and electrical run
  • Bottling and filling station installed

Read More

  • Installation at Fruitspot Cape Town October 2018
  • 4 days to level site for machines and tanks
  • Will produce an average of 5000 litres high quality drinking water per day
  • 50 000 litres storage capacity
  • Water will be pumped into existing storage tanks which are connected to buildings main supply
  • Took 2 days to get machines into place
  • Very little space on the side of the building, had to push machines one by one and rigged them into position